Major Works Project Management for Strata Committees
Major works in a strata scheme can include high-value repairs, planned building upgrades, remediation and replacement of significant common property assets. Examples may include major waterproofing, roof replacement, façade work, lift upgrades, extensive painting, structural rectification and sustainability upgrades. The practical question is whether the work requires substantial planning, specialist input, funding decisions and coordination across the building. The distinction from routine maintenance matters because the governance, budget and communication requirements can be very different.
NSW strata schemes are expected to plan for major expenditure through the capital works fund and the scheme’s long-term planning process. The NSW Government information on strata finances and insurance explains that capital expenses can include replacing or repairing common property and project management and supervision associated with that work. For committees, that means a major works program should sit within the building’s broader financial plan rather than being treated as an isolated contractor job.
Define Objectives and Success Measures
Before seeking quotes, establish what the project needs to achieve. A roof repair may aim to stop recurring water ingress, while a façade program may focus on rectifying defects, protecting the building and restoring external finishes. Objectives help the committee assess options consistently when costs, construction methods or timing vary. They also create a reference point for deciding whether proposed variations are genuinely necessary.
Useful success measures can include completion against the approved scope, controlled project expenditure, safe site conditions, minimal disruption to residents and complete handover records. Linking the project to a broader repairs and maintenance program can also help the committee identify preventative work that should follow the project. Clear measures make committee reporting easier because each progress update can answer what has been completed, what is next and what needs a decision.
Start With the Problem, Not the Contractor
A common planning mistake is to obtain a trade quote before the building problem has been clearly defined. A contractor may be able to describe a repair, but a complex project can require an independent building assessment, engineer, quantity surveyor, designer or other specialist before a tender scope is prepared. The right professional depends on the building element and the nature of the defect.
A good project brief records the observed issue, available evidence, desired outcome, known constraints and information still required. Strata One’s project management service is designed for major refurbishment and defect rectification work and can help committees keep the project organised as it moves from investigation into delivery.
Reports, Design and Scope Development
The quality of the scope has a direct effect on tender quality. Contractors need enough information to understand the work, site conditions, materials, access requirements, exclusions and required standards. Where the scope is vague, each contractor may price a different solution, which makes comparisons difficult and increases the chance of variations later.
For building defects, the committee should retain reports, photographs, drawings, specifications and other relevant evidence in one project record. Where design work is needed, the design documentation should be developed before pricing where practical. The NSW Government guidance on building contracts also reinforces the importance of clear descriptions of work, plans and specifications for applicable building contracts.
Build a Tender Scope That Can Be Compared
- Describe the existing condition and the reason for the project.
- Define the required work and the desired finish or performance outcome.
- State what is included, excluded and allowed only as a variation.
- Identify access, resident, noise, working hours, and protection requirements.
- Specify the documents, warranties, certificates and handover information required.
Budget, Levies and Approvals
Funding should be considered alongside the scope rather than after the tender returns. Committees can compare the projected cost with the capital works fund, existing levy commitments and other planned expenditure. The Strata One guide to capital works funds and special levies provides further context on how long-term planning and special levies relate to major common property expenditure.
NSW Government information confirms that schemes must maintain a capital works fund, with the fund used for capital expenses such as common property replacement and related project management costs. Since April 2026, when an owners corporation revises an existing 10-year plan or prepares a replacement plan after the existing plan has run for 10 years, it must use the standard form for the 10-year plan. Committees should also review the latest official requirements when planning funding and approvals, rather than relying on an older template or past practice.
Allow for the Full Project Cost
A major works budget should account for investigation, reports, design, approvals, contractor work, project management, site protection, professional fees and likely contingencies. It should also consider temporary measures that may be required while the permanent work is being planned. A project that appears affordable on the contractor price alone may become difficult once all supporting costs are added.
Tender and Contractor Selection
Getting comparable tenders requires a consistent scope and a clear tender process. Committees should look beyond the headline price and compare experience with similar strata work, licensing, insurance, proposed methodology, program, exclusions, payment terms, warranties and capacity to work within the building’s access requirements. The NSW Government information on hiring workers for strata notes the importance of considering urgency, licensing, work health and safety obligations, insurance and future budget impacts when engaging workers.
The committee should also document why a tender was preferred. That record helps demonstrate a reasoned decision and gives the strata manager a clear basis for communicating the outcome to owners. For larger or higher risk works, Strata One can coordinate the contractor process as part of project management support and keep the committee informed as the work progresses.
Compare More Than the Price
- Relevant experience with comparable strata buildings and occupied sites.
- Clear scope compliance and transparent exclusions.
- Licence and insurance evidence appropriate to the work.
- Practical project program, access plan and resident communication approach.
- Warranty, defects and handover commitments.
- Capacity to respond to questions and manage agreed reporting requirements.
Program, Site Access and Resident Communication
Major works take place in a shared building, so construction planning needs to account for residents, tenants, visitors, contractors and building operations. A programme should identify noisy works, service interruptions, restricted access areas, deliveries, waste removal and any periods when part of the building cannot be used normally. Early communication reduces surprises and gives residents a clear point of reference when questions arise.
The communication plan should explain what is happening, why the work is needed, what residents need to do and where updates will be posted. Linking project updates to a consistent management process through Strata One’s residential services can help the committee maintain a clear record of notices, decisions and contractor interactions while the building remains occupied.
Keep a Decision Log
Major projects generate many small decisions. Keep a simple decision log showing the date, issue, options considered, decision made, approving body and supporting document. This is particularly useful when a project runs for several months and committee membership changes during the process. A clear record reduces repeated questions and supports continuity.
Quality Checks and Handover
Handover should be treated as part of the project scope from the beginning. The committee should know what records, certificates, warranties, manuals, photographs and maintenance information will be supplied at completion. Without this information, the building may have the physical work completed but still lack the records needed for future maintenance and decision-making.
Quality checks should be planned throughout the project rather than left until the final day. Depending on the work, this may involve staged inspections, photographic records, testing, defect lists and review of invoices against progress. Once complete, the project record should be integrated into the building’s wider repairs and maintenance records so future managers and committees can understand what was done and when.
Close Out With a Practical Handover Pack
- Final scope and approved variations.
- Completion and inspection records.
- Warranties and relevant certificates.
- Updated drawings or asset information where applicable.
- Maintenance recommendations and supplier details.
- Final financial reconciliation and outstanding items.
Major Works Governance Checklist
Before a major works project moves from planning to construction, the committee should be able to answer the following questions. The checklist can also be used as an agenda item for committee meetings so project governance remains visible throughout the program.
- Is the problem clearly documented with reports or evidence?
- Is the scope specific enough for comparable quotes?
- Has the committee confirmed the funding source and likely cash flow?
- Have the required owners corporation approvals been identified?
- Have contractor licensing, insurance and experience been reviewed?
- Is there a programme covering access, disruption and resident notices?
- Are variations subject to a documented approval process?
- Are quality inspections and handover requirements agreed before work starts?
- Will the final project records be stored with the building’s ongoing maintenance information?
For committees that need a broader governance view, the NSW Government strata living guide provides current information on common property, financial obligations, repairs, meetings and other areas of strata administration. It is also sensible to keep the project linked with your scheme’s strata compliance processes so important records and safety obligations are not managed separately from the building’s wider operations.
Bring Your Next Major Works Project Under Control
Major works become easier to manage when the scope, funding, approvals, contractor process, resident communication and handover requirements are planned as one connected project. A structured approach gives committees a clearer basis for decisions and creates a record that can be followed by owners, managers and contractors throughout the work.
If your scheme is preparing for a major repair, refurbishment, remediation or building upgrade, contact Strata One to discuss the project and the support your committee needs. Strata One can assist with the practical coordination of major works while keeping responsibilities, decisions and project information clear.